Sprint Good Practices

Sprint should contain the next items for the team to work on.

  • Everything that requires some coding should end up on a sprint card, developers are required to link a sprint item to complete a pull request.
  • Usually maintained by the project manager, but a developer that receives a service call for an application is also able to create his own card to work autonomously.

When the developer starts working on an item, he should identify that he has started working by :

  • Assigning himself the main card (assigned to) if it's not already assigned to somebody else.
  • Creating a task card and set it to "In Progress", we recommend a simple "On it" card to begin with, but developers might use task cards as a work plan to complete the main card.

A main card is generally marked as "Done" when :

  • The coding tasks are completed
  • The developer has completed his own "coder tests".
  • The pull request has been created, reviewed, fixed and merged
  • The QA has been completed and reworks have been fixed and re-tested.
  • In some cases, the code might be released to production, but it's not mandatory.

Color Scheme​

Action required​

Effort missing​

image (4).avif

Each Product Backlog Item shown on the board should have an estimated effort that is counted in days (1 day = 8hr). This estimated effort should include development and QA effort as well. The analyst might provide an estimate, otherwise, it is the responsibility of the developer to input one to the best of his knowledge when he starts working on the item. In any case, the developer should review the estimate periodically to identify possible overruns as soon as possible. When an overrun is predicted, the developer must advise the project manager as soon as possible.

Effort Too High (bigger than 3 days)​

image (5).avif

To increase efficiency, it is recommended to keep estimated effort for a single PBI to 3 days or less. It is the responsability of the developer to try to break the PBI into multiple items when it's possible to try to reach that limit.

Time Overrun​

image (6).avif

A time overrun will be identified when the total time specified in the Intranet is higher than the estimated effort by less than 15%. The developer should reach out to his project manager to advise him of the situation; he might also need to review the estimated effort if the task is still on-going. We use this for statistical reporting.

Major Overrun​

image (7).avif

A major overrun will be identified when the total time specified in the Intranet is higher than the estimated effort by more than 15%. The developer should reach out to his project manager to advise him of the situation; he might also need to review the estimated effort if the task is still on-going.

We use this for statistical reporting.

Informative​

Blocked​

image (8).avif

This will appear when a card shown on the Sprint has a tag named "Blocked". Adding this tags means that the task is blocked and is waiting for a third-party or something. It is recommended to add a description about the cause in the card description.

QA​

image (9).avif

This identifies QA tasks, it applies only to Task cards for which the titles contains QA.

To help you breakdown your PBI into smaller steps, you might get inspiration from the following chart.

image (10).avif